Elliot's Hill Wind Farm
Elliot's Hill Wind Farm is an operational 5 MW onshore wind farm in Antrim and Newtownabbey, generating since 1 April 1995. Planning permission was granted on 26 October 1994, 11 months after submission. Operator of record: B9 Energy Services Ltd/ ScottishPower Renewables.
Planning and build timeline
| Application submitted | 18 November 1993 |
| Permission granted | 26 October 1994 11 months after submission |
| Operational | 1 April 1995 5 months after consent |
Screening a site of your own?
Antrim and Newtownabbey approves 79% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Elliot's Hill Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Antrim and Newtownabbey’s record on onshore wind
Antrim and Newtownabbey has decided 19 onshore wind schemes and approved 79%, taking a median of 20.4 months. See every onshore wind scheme decision in Antrim and Newtownabbey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 5 | 6.8 km |
Wind Onshore · Operational | 8.8 | 7.7 km |
Solar Photovoltaics · Operational | 6 | 7.7 km |
Wind Onshore · Operational | 2.3 | 8.6 km |
Solar Photovoltaics · Operational | 6.5 | 8.9 km |
Landfill Gas · Operational | 3.2 | 9.1 km |
Solar Photovoltaics · Operational | 4.8 | 9.2 km |
Solar Photovoltaics · Operational | 6.4 | 9.7 km |
How big is Elliot's Hill Wind Farm?
Elliot's Hill Wind Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Elliot's Hill Wind Farm?
REPD records the operator as B9 Energy Services Ltd/ ScottishPower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Elliot's Hill Wind Farm approved and built?
The application was submitted on 18 November 1993. Permission was granted on 26 October 1994, 11 months later. The site became operational on 1 April 1995, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3106.