Renewable sites › Ballymena Wind Park Limited
Ballymena Wind Park Limited
Ballymena Wind Park Limited is operational in Mid and East Antrim with a recorded capacity of 4.7 MW, and has been generating since 2013-01-24.
Planning and build timeline
| Application submitted | 2009-07-24 |
| Permission granted | 2010-04-14 9 months after submission |
| Operational | 2013-01-24 33 months after consent |
Mid and East Antrim’s record on onshore wind
Mid and East Antrim has decided 21 onshore wind schemes and approved 81%, taking a median of 14.6 months. See every onshore wind scheme decision in Mid and East Antrim →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Ballygarvey Road Solar Photovoltaics · Operational | 13 | 1.4 km |
The Michelin Tyre Factory - Ballymena Wind Onshore · Operational | 4.6 | 2.3 km |
Tully Quarry Anaerobic Digestion · Operational | 3 | 5.2 km |
Elginny Hill Wind Onshore · Operational | 22 | 6.5 km |
Rathsherry Wind Onshore · Operational | 21 | 8.8 km |
Corby Knowe Wind Onshore · Operational | 5 | 10.6 km |
Wolf Bog Wind Farm Wind Onshore · Operational | 8.8 | 12.9 km |
Connaught Road Wind Onshore · Operational | 1.7 | 13.5 km |
How big is Ballymena Wind Park Limited?
Ballymena Wind Park Limited has a recorded installed capacity of 4.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ballymena Wind Park Limited?
REPD records the operator as White Young Green Planning. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ballymena Wind Park Limited approved and built?
The application was submitted on 2009-07-24. Permission was granted on 2010-04-14, 9 months later. The site became operational on 2013-01-24, 33 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2866.
Novarly Parcel · official public data, read properly · parcel.novarly.com