Onshore wind planning in Mid and East Antrim

Mid and East Antrim has decided 21 onshore wind schemes and approved 81% of them, taking a median of 14.6 months to decide. Consented capacity: 83 MW. 10 applications still awaiting a decision.

81%
Approved
17 granted · 4 refused
14.6 mo
Median decision
UK 11.5 mo
83 MW
Consented
38 MW refused
5
Appeals
1 allowed on appeal

How Mid and East Antrim compares

Against the 75 UK authorities with 5+ onshore wind decisions, Mid and East Antrim sits in the 78th percentile for approval rate (13 points above the England average) and the 48th percentile for speed.

Decisions by year

35Approved — 2 (2010)210Approved — 1 (2014)Refused — 3 (2014)414Approved — 1 (2015)115Approved — 1 (2016)116Approved — 1 (2017)117Approved — 1 (2019)119Approved — 1 (2020)120Approved — 3 (2021)321Approved — 1 (2022)122Approved — 2 (2023)223Approved — 1 (2024)Refused — 1 (2024)224Approved — 1 (2025)125
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (33)

SchemeMWStatusDecided
Wind Turbine Development in Ballyclare
Private Developer · LA02/2024/0787/F
Application Withdrawn2025-10-23
Wind Turbine Development in Ballymena
Private Developer · LA02/2025/0231/F
Application Submitted2025-03-14
Omerbane Road, Cloughmills - Wind Turbine
Wind Power (NI) Ltd · LA02/2024/0431/F · 7.4 mo to decide
Awaiting Construction2025-01-09
85 Deerfin Road, Ballymena - Wind Turbine
Mc Larnon Roofing Limited · LA02/2023/1373/F · 16.7 mo to decide
0.25Application Refused2024-09-03
Wind Turbine Development in Broughshane
Heron Energy Limited · LA02/2023/1884/F · 3.7 mo to decide
Awaiting Construction2024-02-09
93 Caddy Road - Wind Turbine
Private Developer · LA02/2023/1141/F · 10.2 mo to decide
0.85Awaiting Construction2023-12-01
58 Tullykiagh Road - Wind Turbine
HHT renewables · LA02/2023/1133/F · 5.7 mo to decide
Awaiting Construction2023-07-10
Carnbuck Wind Farm
RES Limited · SPD/2023/0951/F
50.4Application Submitted2023-02-22
Omerbane Road, Cloughmills Replacement
HHT Renewables Limited · LA02/2021/0791/F · 7.2 mo to decide
0.25Awaiting Construction2022-03-24
Unshinagh Wind Farm Development in Carnlough
Renewable Energy Systems (RES) · LA02/2021/1205/F
58.8Application Submitted2021-12-22
Replacement Wind Turbine
Pegasus Planning Group · LA02/2021/0092/F · 5.8 mo to decide
0.15Awaiting Construction2021-07-22
Carmagrim Road
Private Developer · LA02/2020/0045/F · 14.5 mo to decide
0.2Awaiting Construction2021-04-06
Larne Road
Private Developer · LA02/2019/0880/F · 14 mo to decide
0.3Awaiting Construction2021-01-19
Loughmourne Road
Private Developer · LA02/2021/0029/F
Application Submitted2020-12-30
Woodside Road
Brooklands Healthcare · LA02/2019/0935/F · 10.6 mo to decide
0.3Awaiting Construction2020-10-29
Garvaghy Road
Hill Power Limited · LA08/2020/1129/F
Application Submitted2020-10-01
402 metres NE of 45 Dickeystown Road
Glenview Green Energy · LA02/2017/0715/F · 19.7 mo to decide
0.3Awaiting Construction2019-03-28
Carnalbanagh Windfarm
ABO Wind NI · LA02/2017/0594/F
21Application Submitted2017-06-29
Craigs Wind Turbine II
Bulrush Horticulture · LA02/2015/0657/F · 14.8 mo to decide
3Planning Permission Expired2017-01-31
Ballykeel Wind Farm
Wind NI Ltd · F/2013/0244/F · 35.8 mo to decide
16.1Awaiting Construction2016-12-13
Whappstown Wind Farm
TCI Renewables · G/2011/0052/F · 55.7 mo to decide
9.2Revised2015-09-24
Rathsherry
Energia (formerly Brookfield Renewable Energy Group) · G/2011/0162/F · 47.5 mo to decide
21Operational2015-03-26
Feystown Wind Farm
ABO Wind NI · F/2013/0101/F · 19.3 mo to decide
13.8Appeal Refused2014-12-22
Elginny Hill
Brookfields (Antrim Wind Energy) · G/2011/0041/F · 44 mo to decide
22Operational2014-11-13
Cloghinarney
Cloghinarney Wind Farm · G/2011/0155/F · 39.7 mo to decide
13.8Appeal Refused2014-07-29
Mullaghsandall Road wind farm
Apamore Services · F/2013/0085/F · 14.6 mo to decide
10Appeal Refused2014-07-10
Carnalbanagh Wind Farm
ABO Wind NI · G/2014/0182/F
28.5Revised2014-05-30
Douglas Top
Macwindgen Limited · G/2011/0182/F
51Application Withdrawn2012-04-25
Rathsherry
Wheel House Energy · G/2006/0842
11.7Revised2011-02-16
Elginny Hill
Antrim Wind Energy · G/2006/0754/F
20Revised2011-01-17
Ballymena Wind Park Limited
White Young Green Planning · G/2009/0470/F · 8.7 mo to decide
4.7Operational2010-04-14
The Michelin Tyre Factory - Ballymena
Ecotricity · G/2009/0470/FUL · 6.5 mo to decide
4.6Operational2010-02-07
Wolf Bog Wind Farm
B9 Energy / RES · G/2004/1532/F · 18.1 mo to decide
8.8Operational2005-11-02

Does Mid and East Antrim approve onshore wind schemes?

Yes — of the 21 onshore wind schemes Mid and East Antrim has decided, 81% were approved (17 granted, 4 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Mid and East Antrim?

The median time from application to decision is 14.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Mid and East Antrim consented?

83 MW has been consented across 17 approved schemes, with 38 MW refused. A further 10 applications awaits a decision.

Other technologies in Mid and East Antrim

Solar in Mid and East AntrimBattery storage in Mid and East Antrim

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.