Novarly ParcelRenewable sites

Renewable sitesWind Turbine 1

Wind Turbine 1

Wind Turbine 1 is an operational 2.3 MW onshore wind farm in Antrim and Newtownabbey, generating since 30 May 2011. Planning permission was granted on 15 February 2010, 8 months after submission. Operator of record: Brett Martin Ltd.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 30 May 2011
Wind Onshore
Technology
Brett Martin Ltd
Antrim and Newtownabbey
Authority
Northern Ireland

Planning and build timeline

Application submitted2 June 2009
Permission granted15 February 2010
8 months after submission
Operational30 May 2011
15 months after consent

Screening a site of your own?

RedlineUK · £39

Antrim and Newtownabbey approves 79% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Wind Turbine 1’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Antrim and Newtownabbey’s record on onshore wind

Antrim and Newtownabbey has decided 19 onshore wind schemes and approved 79%, taking a median of 20.4 months. See every onshore wind scheme decision in Antrim and Newtownabbey

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
3.20.7 km
Solar Photovoltaics · Operational
6.41.4 km
Solar Photovoltaics · Operational
3.85.4 km
Wind Onshore · Operational
13.88.5 km
Solar Photovoltaics · Operational
108.5 km
Wind Onshore · Operational
58.6 km
Solar Photovoltaics · Operational
4.811.7 km
Anaerobic Digestion · Operational
1.211.7 km

How big is Wind Turbine 1?

Wind Turbine 1 has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wind Turbine 1?

REPD records the operator as Brett Martin Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wind Turbine 1 approved and built?

The application was submitted on 2 June 2009. Permission was granted on 15 February 2010, 8 months later. The site became operational on 30 May 2011, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2830.