Renewable sites › Corby Knowe
Corby Knowe
Corby Knowe is operational in Antrim and Newtownabbey with a recorded capacity of 5 MW, and has been generating since 2017-05-31.
Planning and build timeline
| Application submitted | 2006-11-17 |
| Permission granted | 2013-01-30 74 months after submission |
| Operational | 2017-05-31 52 months after consent |
Antrim and Newtownabbey’s record on onshore wind
Antrim and Newtownabbey has decided 19 onshore wind schemes and approved 79%, taking a median of 20.4 months. See every onshore wind scheme decision in Antrim and Newtownabbey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tully Quarry Anaerobic Digestion · Operational | 3 | 5.4 km |
Wolf Bog Wind Farm Wind Onshore · Operational | 8.8 | 6.4 km |
Millar Farm Solar Photovoltaics · Operational | 6 | 6.7 km |
Elliot's Hill Wind Farm Wind Onshore · Operational | 5 | 6.8 km |
Connaught Road Wind Onshore · Operational | 1.7 | 8.7 km |
The Michelin Tyre Factory - Ballymena Wind Onshore · Operational | 4.6 | 9.3 km |
Ballymena Wind Park Limited Wind Onshore · Operational | 4.7 | 10.6 km |
South Antrim Solar Park - Phase 1 Solar Photovoltaics · Operational | 6.5 | 11.3 km |
How big is Corby Knowe?
Corby Knowe has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Corby Knowe?
REPD records the operator as Gaelectric Developments/ CGN Europe Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Corby Knowe approved and built?
The application was submitted on 2006-11-17. Permission was granted on 2013-01-30, 74 months later. The site became operational on 2017-05-31, 52 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4246.