Renewable sites › Withyhedge Generation Plant
Withyhedge Generation Plant
Withyhedge Generation Plant is operational in Pembrokeshire with a recorded capacity of 2.4 MW, and has been generating since 2007-09-01.
Planning and build timeline
| Application submitted | 1999-12-06 |
| Permission granted | 2000-03-07 3 months after submission |
| Operational | 2007-09-01 90 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rudbaxton Solar Park Solar Photovoltaics · Operational | 10.8 | 0.8 km |
Puffin Produce - Solar Panels Solar Photovoltaics · Operational | — | 3.8 km |
Crundale / Fenton Home Farm (extension) Solar Photovoltaics · Operational | 5.9 | 4.1 km |
Fenton Home Farm Solar Photovoltaics · Operational | 31.3 | 4.8 km |
Shoals Hook Farm Solar Photovoltaics · Operational | 12.1 | 5 km |
Cuckoo Grove Farm Solar Photovoltaics · Operational | 6.1 | 6.5 km |
Oak Cottage Solar Photovoltaics · Operational | 4.9 | 7.3 km |
AMBLESTON SOLAR PANELS Solar Photovoltaics · Operational | 6 | 7.5 km |
How big is Withyhedge Generation Plant?
Withyhedge Generation Plant has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Withyhedge Generation Plant?
REPD records the operator as Unknown. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Withyhedge Generation Plant approved and built?
The application was submitted on 1999-12-06. Permission was granted on 2000-03-07, 3 months later. The site became operational on 2007-09-01, 90 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 603.