Withyhedge Generation Plant

Withyhedge Generation Plant is an operational 2.4 MW landfill gas site in Pembrokeshire, generating since 1 September 2007. Planning permission was granted on 7 March 2000, 3 months after submission. Operator of record: Unknown.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2007
Landfill Gas
Technology
Unknown
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted6 December 1999
Permission granted7 March 2000
3 months after submission
Operational1 September 2007
90 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Pembrokeshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Withyhedge Generation Plant’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
10.80.8 km
Solar Photovoltaics · Operational
3.8 km
Solar Photovoltaics · Operational
5.94.1 km
Solar Photovoltaics · Operational
31.34.8 km
Solar Photovoltaics · Operational
12.15 km
Solar Photovoltaics · Operational
6.16.5 km
Solar Photovoltaics · Operational
4.97.3 km
Solar Photovoltaics · Operational
67.5 km

How big is Withyhedge Generation Plant?

Withyhedge Generation Plant has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Withyhedge Generation Plant?

REPD records the operator as Unknown. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Withyhedge Generation Plant approved and built?

The application was submitted on 6 December 1999. Permission was granted on 7 March 2000, 3 months later. The site became operational on 1 September 2007, 90 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 603.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode