AMBLESTON SOLAR PANELS is operational in Pembrokeshire with a recorded capacity of 6 MW, and has been generating since 2012-01-25.
Planning and build timeline
| Application submitted | 2011-06-16 |
| Permission granted | 2011-08-11 2 months after submission |
| Operational | 2012-01-25 5 months after consent |
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Withyhedge Generation Plant Landfill Gas · Operational | 2.4 | 7.5 km |
Rudbaxton Solar Park Solar Photovoltaics · Operational | 10.8 | 8.1 km |
Oak Cottage Solar Photovoltaics · Operational | 4.9 | 8.5 km |
Crundale / Fenton Home Farm (extension) Solar Photovoltaics · Operational | 5.9 | 9.4 km |
Fenton Home Farm Solar Photovoltaics · Operational | 31.3 | 9.6 km |
Puffin Produce - Solar Panels Solar Photovoltaics · Operational | — | 10.5 km |
Shoals Hook Farm Solar Photovoltaics · Operational | 12.1 | 10.9 km |
Langton Farm Solar park Solar Photovoltaics · Operational | 4.4 | 11.4 km |
How big is AMBLESTON SOLAR PANELS?
AMBLESTON SOLAR PANELS has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates AMBLESTON SOLAR PANELS?
REPD records the operator as Arqiva Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was AMBLESTON SOLAR PANELS approved and built?
The application was submitted on 2011-06-16. Permission was granted on 2011-08-11, 2 months later. The site became operational on 2012-01-25, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1623.