Renewable sites › Fenton Home Farm
Fenton Home Farm
Fenton Home Farm is an operational 31.3 MW solar farm in Pembrokeshire, generating since 12 September 2014. Planning permission was granted on 5 December 2013, 5 months after submission. Operator of record: Sunsave.
Planning and build timeline
| Application submitted | 2 July 2013 |
| Permission granted | 5 December 2013 5 months after submission |
| Operational | 12 September 2014 9 months after consent |
Screening a site of your own?
Pembrokeshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Fenton Home Farm’s recorded coordinate — swap in your own postcode or coordinates.
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5.9 | 0.8 km |
Solar Photovoltaics · Operational | 12.1 | 1.7 km |
Solar Photovoltaics · Operational | — | 2.8 km |
Solar Photovoltaics · Operational | 4.9 | 4 km |
Solar Photovoltaics · Operational | 10.8 | 4.1 km |
Landfill Gas · Operational | 2.4 | 4.8 km |
Solar Photovoltaics · Operational | 6.1 | 6.2 km |
Solar Photovoltaics · Operational | 5 | 6.7 km |
How big is Fenton Home Farm?
Fenton Home Farm has a recorded installed capacity of 31.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Fenton Home Farm?
REPD records the operator as Sunsave. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Fenton Home Farm approved and built?
The application was submitted on 2 July 2013. Permission was granted on 5 December 2013, 5 months later. The site became operational on 12 September 2014, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1765.