Renewable sites › Shoals Hook Farm
Shoals Hook Farm
Shoals Hook Farm is operational in Pembrokeshire with a recorded capacity of 12.1 MW, and has been generating since 2015-03-31.
Planning and build timeline
| Application submitted | 2014-05-06 |
| Permission granted | 2014-10-03 5 months after submission |
| Operational | 2015-03-31 6 months after consent |
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crundale / Fenton Home Farm (extension) Solar Photovoltaics · Operational | 5.9 | 1.5 km |
Puffin Produce - Solar Panels Solar Photovoltaics · Operational | — | 1.7 km |
Fenton Home Farm Solar Photovoltaics · Operational | 31.3 | 1.7 km |
Rudbaxton Solar Park Solar Photovoltaics · Operational | 10.8 | 4.1 km |
Cuckoo Grove Farm Solar Photovoltaics · Operational | 6.1 | 4.5 km |
Withyhedge Generation Plant Landfill Gas · Operational | 2.4 | 5 km |
North Tenement Solar Photovoltaics · Operational | 5 | 5.2 km |
Popehill Farm Solar Photovoltaics · Operational | 5 | 5.4 km |
How big is Shoals Hook Farm?
Shoals Hook Farm has a recorded installed capacity of 12.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Shoals Hook Farm?
REPD records the operator as John Laing Environmental Assets Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Shoals Hook Farm approved and built?
The application was submitted on 2014-05-06. Permission was granted on 2014-10-03, 5 months later. The site became operational on 2015-03-31, 6 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2180.
Novarly Parcel · official public data, read properly · parcel.novarly.com