Renewable sites › Oak Cottage
Oak Cottage
Oak Cottage is an operational 4.9 MW solar farm in Pembrokeshire, generating since 21 August 2015. Planning permission was granted on 13 June 2014, 4 months after submission. Operator of record: Anesco.
Planning and build timeline
| Application submitted | 28 January 2014 |
| Permission granted | 13 June 2014 4 months after submission |
| Operational | 21 August 2015 14 months after consent |
Screening a site of your own?
Pembrokeshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Oak Cottage’s recorded coordinate — swap in your own postcode or coordinates.
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 31.3 | 4 km |
Solar Photovoltaics · Operational | 5.9 | 4.6 km |
Solar Photovoltaics · Operational | 12.1 | 5.7 km |
Solar Photovoltaics · Operational | — | 6.7 km |
Solar Photovoltaics · Operational | 10.8 | 7 km |
Landfill Gas · Operational | 2.4 | 7.3 km |
Solar Photovoltaics · Operational | 6 | 8.5 km |
Solar Photovoltaics · Operational | 6.1 | 9.6 km |
How big is Oak Cottage?
Oak Cottage has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Oak Cottage?
REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Oak Cottage approved and built?
The application was submitted on 28 January 2014. Permission was granted on 13 June 2014, 4 months later. The site became operational on 21 August 2015, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1774.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode