Novarly ParcelRenewable sites

Renewable sitesCuckoo Grove Farm

Cuckoo Grove Farm

Cuckoo Grove Farm is operational in Pembrokeshire with a recorded capacity of 6.1 MW, and has been generating since 2015-03-26.

6.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-26
Solar Photovoltaics
Technology
Foresight
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted2012-11-09
Permission granted2013-04-25
5 months after submission
Operational2015-03-26
23 months after consent

Pembrokeshire’s record on solar

Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire

Other built sites within 15 km

SiteMWDistance
Puffin Produce - Solar Panels
Solar Photovoltaics · Operational
3.7 km
North Tenement
Solar Photovoltaics · Operational
53.9 km
Lawrence Landfill
Wind Onshore · Operational
1.64 km
Popehill Farm
Solar Photovoltaics · Operational
54.3 km
Shoals Hook Farm
Solar Photovoltaics · Operational
12.14.5 km
Bolton Hill WTW
Solar Photovoltaics · Operational
0.55.6 km
Crundale / Fenton Home Farm (extension)
Solar Photovoltaics · Operational
5.95.7 km
Rudbaxton Solar Park
Solar Photovoltaics · Operational
10.85.9 km

How big is Cuckoo Grove Farm?

Cuckoo Grove Farm has a recorded installed capacity of 6.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cuckoo Grove Farm?

REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cuckoo Grove Farm approved and built?

The application was submitted on 2012-11-09. Permission was granted on 2013-04-25, 5 months later. The site became operational on 2015-03-26, 23 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2376.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council