Novarly ParcelRenewable sites

Renewable sitesWinwick

Winwick

Winwick is operational in West Northamptonshire with a recorded capacity of 12.3 MW, and has been generating since 2016-06-30.

12.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-06-30
Wind Onshore
Technology
Blue Energy
West Northamptonshire
Authority
England

Planning and build timeline

Application submitted2010-05-17
Permission granted2012-07-13
26 months after submission
Operational2016-06-30
48 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Northamptonshire’s record on onshore wind

West Northamptonshire has decided 12 onshore wind schemes and approved 67%, taking a median of 17.6 months. See every onshore wind scheme decision in West Northamptonshire

Other built sites within 15 km

SiteMWDistance
Lowther Farms
Solar Photovoltaics · Operational
1.82.7 km
Portley Ford Landfill Site
Landfill Gas · Operational
1.83.1 km
Crick Road
Solar Photovoltaics · Under Construction
49.95.1 km
Watford Lodge
Wind Onshore · Operational
12.55.3 km
Yelvertoft Wind Farm
Wind Onshore · Operational
166.1 km
M1 J18 Wind Turbines
Wind Onshore · Operational
46.7 km
East Haddon - Solar Photovoltaic System
Solar Photovoltaics · Under Construction
27.1 km
Lilbourne Wind Farm
Wind Onshore · Operational
107.8 km

How big is Winwick?

Winwick has a recorded installed capacity of 12.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Winwick?

REPD records the operator as Blue Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Winwick approved and built?

The application was submitted on 2010-05-17. Permission was granted on 2012-07-13, 26 months later. The site became operational on 2016-06-30, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4164.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council