Novarly ParcelRenewable sites

Renewable sitesWatford Lodge

Watford Lodge

Watford Lodge is an operational 12.5 MW onshore wind farm in West Northamptonshire, generating since 23 November 2015. Planning permission was granted on 21 December 2011, 40 months after submission. Operator of record: Broadview Energy.

12.5 MW
Capacity
as recorded in REPD
Operational
Status
since 23 November 2015
Wind Onshore
Technology
Broadview Energy
West Northamptonshire
Authority
England

Planning and build timeline

Application submitted19 August 2008
Permission granted21 December 2011
40 months after submission
Operational23 November 2015
47 months after consent

Screening a site of your own?

RedlineUK · £39

West Northamptonshire approves 67% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Watford Lodge’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Northamptonshire’s record on onshore wind

West Northamptonshire has decided 12 onshore wind schemes and approved 67%, taking a median of 17.6 months. See every onshore wind scheme decision in West Northamptonshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
49.94.2 km
Landfill Gas · Operational
14.2 km
Wind Onshore · Operational
44.3 km
Wind Onshore · Operational
12.35.3 km
Solar Photovoltaics · Under Construction
25.7 km
Wind Onshore · Operational
166.2 km
Solar Photovoltaics · Operational
1.86.7 km
Landfill Gas · Operational
1.88.4 km

How big is Watford Lodge?

Watford Lodge has a recorded installed capacity of 12.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Watford Lodge?

REPD records the operator as Broadview Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Watford Lodge approved and built?

The application was submitted on 19 August 2008. Permission was granted on 21 December 2011, 40 months later. The site became operational on 23 November 2015, 47 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4424.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode