Renewable sites › Lowther Farms
Lowther Farms
Lowther Farms is operational in West Northamptonshire with a recorded capacity of 1.8 MW, and has been generating since 2014-07-28.
Planning and build timeline
| Application submitted | 2014-01-07 |
| Permission granted | 2014-04-15 3 months after submission |
| Operational | 2014-07-28 3 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
West Northamptonshire’s record on solar
West Northamptonshire has decided 61 solar farms and approved 92%, taking a median of 2.9 months. See every solar farm decision in West Northamptonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Winwick Wind Onshore · Operational | 12.3 | 2.7 km |
Portley Ford Landfill Site Landfill Gas · Operational | 1.8 | 3.1 km |
East Haddon - Solar Photovoltaic System Solar Photovoltaics · Under Construction | 2 | 6.2 km |
Kelmarsh Wind Farm (Resubmission) Wind Onshore · Operational | 12.5 | 6.5 km |
Watford Lodge Wind Onshore · Operational | 12.5 | 6.7 km |
Crick Road Solar Photovoltaics · Under Construction | 49.9 | 7.6 km |
Yelvertoft Wind Farm Wind Onshore · Operational | 16 | 8.8 km |
M1 J18 Wind Turbines Wind Onshore · Operational | 4 | 9.2 km |
How big is Lowther Farms?
Lowther Farms has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lowther Farms?
REPD records the operator as Lowther Farms. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lowther Farms approved and built?
The application was submitted on 2014-01-07. Permission was granted on 2014-04-15, 3 months later. The site became operational on 2014-07-28, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1500.
Novarly Parcel · official public data, read properly · parcel.novarly.com