Onshore wind planning in West Northamptonshire

West Northamptonshire has decided 12 onshore wind schemes and approved 67% of them, taking a median of 17.6 months to decide. Consented capacity: 76 MW.

67%
Approved
8 granted · 4 refused
17.6 mo
Median decision
UK 11.5 mo
76 MW
Consented
48 MW refused
7
Appeals
5 allowed on appeal

How West Northamptonshire compares

Against the 75 UK authorities with 5+ onshore wind decisions, West Northamptonshire sits in the 45th percentile for approval rate (1 points below the England average) and the 26th percentile for speed.

Decisions by year

35Approved — 1 (2010)Refused — 1 (2010)210Approved — 3 (2011)Refused — 1 (2011)411Approved — 2 (2012)212Approved — 2 (2013)213Refused — 1 (2014)114
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (14)

SchemeMWStatusDecided
Watford Gap Wind Farm
Gamesa Energy · DA/2011/0850 · 30.3 mo to decide
10Application Refused2014-04-23
M1 Wind Farm
Wind Prospect Developments · S/2011/1421/MAF · 18 mo to decide
7.2Operational2013-05-09
M1 J18 Wind Turbines
Airvolution Energy · DA/2011/0742 · 17.1 mo to decide
4Operational2013-02-12
Winwick
Blue Energy · DA/2010/0400 · 25.9 mo to decide
12.3Operational2012-07-13
Lilbourne Wind Farm
Cetis · DA/2009/0731 · 32.7 mo to decide
10Operational2012-07-06
Watford Lodge
Broadview Energy · DA/2009/0620 · 40 mo to decide
12.5Operational2011-12-21
Kelmarsh Wind Farm (Resubmission)
Blue Energy · DA/2010/0100 · 22.3 mo to decide
12.5Operational2011-12-19
Boddington Reservoir
Unknown · DA/2011/0150 · 9.3 mo to decide
1.5Operational2011-12-15
Spring Farm Ridge
Broadview Energy · S/2010/1437/MAF · 8.3 mo to decide
15Application Refused2011-06-30
Yelvertoft Wind Farm
Greencoat UK Wind · DA/2009/0350 · 14.2 mo to decide
16Operational2010-07-20
Draughton Maidwell Wind Farm
Nuon UK · DA/2009/0168� · 9.9 mo to decide
21Appeal Refused2010-01-27
Brixworth Windfarm
Bolsterstone Plc · DA/2008/1252
13Application Withdrawn2009-03-11
Mercedes-Benz Technology Centre
Mercedes-Benz · DA/2008/0997
4Application Withdrawn2008-12-11
Asda Brackmills Distribution Depot
Asda · 07/0356/FULWNN · 10.9 mo to decide
2Application Refused2008-11-04

Does West Northamptonshire approve onshore wind schemes?

Yes — of the 12 onshore wind schemes West Northamptonshire has decided, 67% were approved (8 granted, 4 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in West Northamptonshire?

The median time from application to decision is 17.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has West Northamptonshire consented?

76 MW has been consented across 8 approved schemes, with 48 MW refused. There are no applications currently awaiting a decision.

Other technologies in West Northamptonshire

Solar in West NorthamptonshireBattery storage in West Northamptonshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.