Renewable sites › Teeside Offshore Wind Farm
Teeside Offshore Wind Farm
Teeside Offshore Wind Farm is operational in DECC (S36) with a recorded capacity of 62 MW, and has been generating since 2013-08-31.
Planning and build timeline
| Application submitted | 2005-03-22 |
| Permission granted | 2007-09-17 30 months after submission |
| Operational | 2013-08-31 71 months after consent |
What this site sits on
- Special Protection Area — Teesmouth and Cleveland Coast
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Kirkleatham Street - Solar Panel Array Solar Photovoltaics · Under Construction | 0.17 | 3.6 km |
ICI No2 (Teesport) Landfill Landfill Gas · Operational | 1 | 7.1 km |
Dean Group Business Park - Hartlepool Anaerobic Digestion · Operational | 5.1 | 7.1 km |
Wilton 11 EfW EfW Incineration · Operational | 49 | 8.7 km |
Wilton International Biomass (dedicated) · Operational | 35.2 | 8.7 km |
Imperial Park Anaerobic Digestion · Operational | 5.1 | 9.1 km |
Port Clarence Biomass Plant Biomass (dedicated) · Under Construction | 40 | 10.8 km |
Land at Bluehouse Farm Solar Photovoltaics · Operational | 5 | 11.3 km |
How big is Teeside Offshore Wind Farm?
Teeside Offshore Wind Farm has a recorded installed capacity of 62 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Teeside Offshore Wind Farm?
REPD records the operator as EDF Energy - Northern Offshore Windfarm Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Teeside Offshore Wind Farm approved and built?
The application was submitted on 2005-03-22. Permission was granted on 2007-09-17, 30 months later. The site became operational on 2013-08-31, 71 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2514.