Novarly ParcelRenewable sites

Renewable sitesWhites Landfill Site (Canford)

Whites Landfill Site (Canford)

Whites Landfill Site (Canford) is operational in Bournemouth, Christchurch and Poole with a recorded capacity of 6 MW, and has been generating since 1996-05-01.

6 MW
Capacity
as recorded in REPD
Operational
Status
since 1996-05-01
Landfill Gas
Technology
Canford Renewable Energy Ltd
Bournemouth, Christchurch and Poole
Authority
England

Planning and build timeline

Application submitted1993-01-28
Permission granted1993-05-13
3 months after submission
Operational1996-05-01
36 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Canford
Advanced Conversion Technologies · Under Construction
100.5 km
Dorset Green Battery
Battery · Operational
0.6 km
Dorset Green Hydrogen
Hydrogen · Operational
0.90.6 km
Dorset Green Solar Farm
Solar Photovoltaics · Operational
50.6 km
Holes Bay
Battery · Operational
155.1 km
Beacon Hill
Landfill Gas · Operational
35.2 km
Bedborough Farm
Solar Photovoltaics · Operational
76 km
Woodtown Farm
Solar Photovoltaics · Operational
3.86.2 km

How big is Whites Landfill Site (Canford)?

Whites Landfill Site (Canford) has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Whites Landfill Site (Canford)?

REPD records the operator as Canford Renewable Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Whites Landfill Site (Canford) approved and built?

The application was submitted on 1993-01-28. Permission was granted on 1993-05-13, 3 months later. The site became operational on 1996-05-01, 36 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 586.