Renewable sites › Dorset Green Solar Farm
Dorset Green Solar Farm
Dorset Green Solar Farm is operational in Bournemouth, Christchurch and Poole with a recorded capacity of 5 MW, and has been generating since 2023-04-05.
Planning and build timeline
| Application submitted | 2021-03-12 |
| Permission granted | 2021-07-23 4 months after submission |
| Operational | 2023-04-05 20 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Bournemouth, Christchurch and Poole
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Bournemouth, Christchurch and Poole’s record on solar
Bournemouth, Christchurch and Poole has decided 25 solar farms and approved 88%, taking a median of 2.3 months. See every solar farm decision in Bournemouth, Christchurch and Poole →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dorset Green Battery Battery · Operational | — | 0 km |
Dorset Green Hydrogen Hydrogen · Operational | 0.9 | 0 km |
Canford Advanced Conversion Technologies · Under Construction | 10 | 0.1 km |
Whites Landfill Site (Canford) Landfill Gas · Operational | 6 | 0.6 km |
Bedborough Farm Solar Photovoltaics · Operational | 7 | 5.6 km |
Holes Bay Battery · Operational | 15 | 5.6 km |
Woodtown Farm Solar Photovoltaics · Operational | 3.8 | 5.6 km |
Beacon Hill Landfill Gas · Operational | 3 | 5.8 km |
How big is Dorset Green Solar Farm?
Dorset Green Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dorset Green Solar Farm?
REPD records the operator as Canford Renewable Energy Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dorset Green Solar Farm approved and built?
The application was submitted on 2021-03-12. Permission was granted on 2021-07-23, 4 months later. The site became operational on 2023-04-05, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8858.