Renewable sitesDorset Green Hydrogen

Dorset Green Hydrogen

Dorset Green Hydrogen is operational in Bournemouth, Christchurch and Poole with a recorded capacity of 0.9 MW, and has been generating since 2023-04-05.

0.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-04-05
Hydrogen
Technology
Canford Renewable Energy Limited
Bournemouth, Christchurch and Poole
Authority
England

Planning and build timeline

Application submitted2021-03-12
Permission granted2021-07-27
5 months after submission
Operational2023-04-05
20 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Dorset Green Solar Farm
Solar Photovoltaics · Operational
50 km
Dorset Green Battery
Battery · Operational
0 km
Canford
Advanced Conversion Technologies · Under Construction
100.1 km
Whites Landfill Site (Canford)
Landfill Gas · Operational
60.6 km
Bedborough Farm
Solar Photovoltaics · Operational
75.6 km
Holes Bay
Battery · Operational
155.6 km
Woodtown Farm
Solar Photovoltaics · Operational
3.85.6 km
Beacon Hill
Landfill Gas · Operational
35.8 km

How big is Dorset Green Hydrogen?

Dorset Green Hydrogen has a recorded installed capacity of 0.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dorset Green Hydrogen?

REPD records the operator as Canford Renewable Energy Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dorset Green Hydrogen approved and built?

The application was submitted on 2021-03-12. Permission was granted on 2021-07-27, 5 months later. The site became operational on 2023-04-05, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12862.