Renewable sites › Holes Bay
Holes Bay
Holes Bay is operational in Bournemouth, Christchurch and Poole with a recorded capacity of 15 MW, and has been generating since 2020-06-01.
Planning and build timeline
| Application submitted | 2017-02-08 |
| Permission granted | 2017-09-07 7 months after submission |
| Operational | 2020-06-01 33 months after consent |
What this site sits on
- Nutrient-neutrality catchment — Poole Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Beacon Hill Landfill Gas · Operational | 3 | 4.2 km |
Whites Landfill Site (Canford) Landfill Gas · Operational | 6 | 5.1 km |
Canford Advanced Conversion Technologies · Under Construction | 10 | 5.5 km |
Race farm Solar Photovoltaics · Operational | 6.1 | 5.6 km |
Dorset Green Hydrogen Hydrogen · Operational | 0.9 | 5.6 km |
Dorset Green Solar Farm Solar Photovoltaics · Operational | 5 | 5.6 km |
Dorset Green Battery Battery · Operational | — | 5.6 km |
Henbury Quarry Solar Photovoltaics · Operational | 3.9 | 6.6 km |
How big is Holes Bay?
Holes Bay has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Holes Bay?
REPD records the operator as Harmony Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Holes Bay approved and built?
The application was submitted on 2017-02-08. Permission was granted on 2017-09-07, 7 months later. The site became operational on 2020-06-01, 33 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7688.