Bedborough Farm is operational in Dorset with a recorded capacity of 7 MW, and has been generating since 2016-02-26.

7 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-02-26
Solar Photovoltaics
Technology
Solstice Renewables Ltd
Dorset
Authority
England

Planning and build timeline

Application submitted2014-08-14
Permission granted2014-11-03
3 months after submission
Operational2016-02-26
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Dorset’s record on solar

Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset

Other built sites within 15 km

SiteMWDistance
Mannington Battery Energy Storage System
Battery · Under Construction
49.93.8 km
Chapel Lane Parley Solar Farm Phase 3
Solar Photovoltaics · Operational
44.5 km
Wedgehill Farm
Solar Photovoltaics · Operational
135.2 km
Chapel Lane Parley Solar Farm Phase 1
Solar Photovoltaics · Operational
205.3 km
Homeland Solar Farm
Solar Photovoltaics · Operational
13.25.3 km
Chapel Lane Parley Solar Farm Phase 2
Solar Photovoltaics · Operational
365.4 km
Dorset Green Solar Farm
Solar Photovoltaics · Operational
55.6 km
Dorset Green Battery
Battery · Operational
5.6 km

How big is Bedborough Farm?

Bedborough Farm has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bedborough Farm?

REPD records the operator as Solstice Renewables Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bedborough Farm approved and built?

The application was submitted on 2014-08-14. Permission was granted on 2014-11-03, 3 months later. The site became operational on 2016-02-26, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2114.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council