Whitelee
Whitelee is operational in Scottish Government (S36) with a recorded capacity of 322 MW, and has been generating since 2007-12-14.
Planning and build timeline
| Application submitted | 2002-01-23 |
| Permission granted | 2006-04-01 50 months after submission |
| Operational | 2007-12-14 20 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Whitelee Windfarm Extension Phase 1 Wind Onshore · Operational | 108 | 0.7 km |
National Wind Turbine Test Site Wind Onshore · Operational | 4.7 | 1.1 km |
Myres Hill Wind Onshore · Operational | 1.8 | 1.2 km |
Ardoch and Over Enoch Wind Farm (Over Enoch) Wind Onshore · Operational | 4.3 | 3.6 km |
Ardoch and Over Enoch Wind Farm (Ardoch) Wind Onshore · Operational | 7.2 | 4.6 km |
West Browncastle Wind Onshore · Operational | 30 | 5 km |
Whitelee Windfarm Extension phase 2 Wind Onshore · Operational | 109 | 5.2 km |
Calder Water Community Wind Farm Wind Onshore · Operational | 28 | 6.5 km |
How big is Whitelee?
Whitelee has a recorded installed capacity of 322 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Whitelee?
REPD records the operator as CRE Energy/ Scottish Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Whitelee approved and built?
The application was submitted on 2002-01-23. Permission was granted on 2006-04-01, 50 months later. The site became operational on 2007-12-14, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3489.