Renewable sites › Whitelee
Whitelee
Whitelee is an operational 322 MW onshore wind farm in Scotland, generating since 14 December 2007. Planning permission was granted on 1 April 2006, 50 months after submission. Operator of record: CRE Energy/ Scottish Power.
Planning and build timeline
| Application submitted | 23 January 2002 |
| Permission granted | 1 April 2006 50 months after submission |
| Operational | 14 December 2007 20 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Whitelee’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 108 | 0.7 km |
Wind Onshore · Operational | 4.7 | 1.1 km |
Wind Onshore · Operational | 1.8 | 1.2 km |
Wind Onshore · Operational | 4.3 | 3.6 km |
Wind Onshore · Operational | 7.2 | 4.6 km |
Wind Onshore · Operational | 30 | 5 km |
Wind Onshore · Operational | 109 | 5.2 km |
Wind Onshore · Operational | 28 | 6.5 km |
How big is Whitelee?
Whitelee has a recorded installed capacity of 322 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Whitelee?
REPD records the operator as CRE Energy/ Scottish Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Whitelee approved and built?
The application was submitted on 23 January 2002. Permission was granted on 1 April 2006, 50 months later. The site became operational on 14 December 2007, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3489.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode