Renewable sites › Myres Hill
Myres Hill
Myres Hill is operational in East Renfrewshire with a recorded capacity of 1.8 MW, and has been generating since 2001-11-01.
Planning and build timeline
| Application submitted | 1999-05-01 |
| Permission granted | 2001-08-31 28 months after submission |
| Operational | 2001-11-01 2 months after consent |
East Renfrewshire’s record on onshore wind
East Renfrewshire has decided 10 onshore wind schemes and approved 80%, taking a median of 19.6 months. See every onshore wind scheme decision in East Renfrewshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
National Wind Turbine Test Site Wind Onshore · Operational | 4.7 | 0.4 km |
Whitelee Wind Onshore · Operational | 322 | 1.2 km |
Whitelee Windfarm Extension Phase 1 Wind Onshore · Operational | 108 | 1.7 km |
Ardoch and Over Enoch Wind Farm (Over Enoch) Wind Onshore · Operational | 4.3 | 2.6 km |
Ardoch and Over Enoch Wind Farm (Ardoch) Wind Onshore · Operational | 7.2 | 3.5 km |
West Browncastle Wind Onshore · Operational | 30 | 5.7 km |
Whitelee Windfarm Extension phase 2 Wind Onshore · Operational | 109 | 6.3 km |
Whitelee Wind Farm Battery Storage Extension Battery · Operational | 50 | 6.8 km |
How big is Myres Hill?
Myres Hill has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Myres Hill?
REPD records the operator as National Energy Laboratories (NEL). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Myres Hill approved and built?
The application was submitted on 1999-05-01. Permission was granted on 2001-08-31, 28 months later. The site became operational on 2001-11-01, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3090.
Novarly Parcel · official public data, read properly · parcel.novarly.com