Renewable sites › Ardoch and Over Enoch Wind Farm (Ardoch)
Ardoch and Over Enoch Wind Farm (Ardoch)
Ardoch and Over Enoch Wind Farm (Ardoch) is an operational 7.2 MW onshore wind farm in East Renfrewshire, generating since 12 November 2014. Planning permission was granted on 9 July 2012, 2 months after submission. Operator of record: 2020 Renewables/ NTR.
Planning and build timeline
| Application submitted | 24 May 2012 |
| Permission granted | 9 July 2012 2 months after submission |
| Operational | 12 November 2014 28 months after consent |
Screening a site of your own?
East Renfrewshire approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Ardoch and Over Enoch Wind Farm (Ardoch)’s recorded coordinate — swap in your own postcode or coordinates.
East Renfrewshire’s record on onshore wind
East Renfrewshire has decided 10 onshore wind schemes and approved 80%, taking a median of 19.6 months. See every onshore wind scheme decision in East Renfrewshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4.3 | 1.1 km |
Wind Onshore · Operational | 1.8 | 3.5 km |
Wind Onshore · Operational | 4.7 | 3.8 km |
Wind Onshore · Operational | 322 | 4.6 km |
Wind Onshore · Operational | 108 | 5.2 km |
Solar Photovoltaics · Under Construction | 0.94 | 5.5 km |
Battery · Operational | 50 | 5.8 km |
Wind Onshore · Operational | 30 | 7.3 km |
How big is Ardoch and Over Enoch Wind Farm (Ardoch)?
Ardoch and Over Enoch Wind Farm (Ardoch) has a recorded installed capacity of 7.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ardoch and Over Enoch Wind Farm (Ardoch)?
REPD records the operator as 2020 Renewables/ NTR. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ardoch and Over Enoch Wind Farm (Ardoch) approved and built?
The application was submitted on 24 May 2012. Permission was granted on 9 July 2012, 2 months later. The site became operational on 12 November 2014, 28 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3925.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode