Renewable sitesCalder Water Community Wind Farm

Calder Water Community Wind Farm

Calder Water Community Wind Farm is an operational 28 MW onshore wind farm in South Lanarkshire, generating since 1 September 2013. Planning permission was granted on 29 November 2011, 27 months after submission. Operator of record: Community Windpower (Community Wind Power).

28 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2013
Wind Onshore
Technology
Community Windpower (Community Wind Power)
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted26 August 2009
Permission granted29 November 2011
27 months after submission
Operational1 September 2013
21 months after consent

Screening a site of your own?

RedlineUK · £39

South Lanarkshire approves 73% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Calder Water Community Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
302.4 km
Wind Onshore · Under Construction
365.8 km
Wind Onshore · Operational
3226.5 km
Wind Onshore · Operational
1086.5 km
Wind Onshore · Operational
1096.7 km
Battery · Operational
506.9 km
Wind Onshore · Operational
1.87.4 km
Wind Onshore · Operational
4.77.5 km

How big is Calder Water Community Wind Farm?

Calder Water Community Wind Farm has a recorded installed capacity of 28 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Calder Water Community Wind Farm?

REPD records the operator as Community Windpower (Community Wind Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Calder Water Community Wind Farm approved and built?

The application was submitted on 26 August 2009. Permission was granted on 29 November 2011, 27 months later. The site became operational on 1 September 2013, 21 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3688.