Renewable sitesNational Wind Turbine Test Site

National Wind Turbine Test Site

National Wind Turbine Test Site is an operational 4.7 MW onshore wind farm in East Renfrewshire, generating since 15 February 2001. Planning permission was granted on 1 August 2000, 11 months after submission. Operator of record: NEL.

4.7 MW
Capacity
as recorded in REPD
Operational
Status
since 15 February 2001
Wind Onshore
Technology
NEL
East Renfrewshire
Authority
Scotland

Planning and build timeline

Application submitted19 August 1999
Permission granted1 August 2000
11 months after submission
Operational15 February 2001
7 months after consent

Screening a site of your own?

RedlineUK · £39

East Renfrewshire approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with National Wind Turbine Test Site’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

East Renfrewshire’s record on onshore wind

East Renfrewshire has decided 10 onshore wind schemes and approved 80%, taking a median of 19.6 months. See every onshore wind scheme decision in East Renfrewshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
1.80.4 km
Wind Onshore · Operational
3221.1 km
Wind Onshore · Operational
1081.5 km
Wind Onshore · Operational
4.33 km
Wind Onshore · Operational
7.23.8 km
Wind Onshore · Operational
305.9 km
Wind Onshore · Operational
1096.1 km
Battery · Operational
507.1 km

How big is National Wind Turbine Test Site?

National Wind Turbine Test Site has a recorded installed capacity of 4.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates National Wind Turbine Test Site?

REPD records the operator as NEL. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was National Wind Turbine Test Site approved and built?

The application was submitted on 19 August 1999. Permission was granted on 1 August 2000, 11 months later. The site became operational on 15 February 2001, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3093.