Renewable sites › West Knock Wind Cluster
West Knock Wind Cluster
West Knock Wind Cluster is operational in Aberdeenshire with a recorded capacity of 2.4 MW, and has been generating since 2011-10-04.
Planning and build timeline
| Application submitted | 2009-07-27 |
| Permission granted | 2011-04-21 21 months after submission |
| Operational | 2011-10-04 5 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Yonderton Farm Wind Onshore · Operational | 1 | 8.7 km |
Hill of Skilmafilly Cloffrickford (Denmore) Wind Farm Wind Onshore · Operational | 6.9 | 9.4 km |
Upper Ardgrain Wind Farm Wind Onshore · Operational | 2.4 | 9.9 km |
Stoneyhill Landfill Site Landfill Gas · Operational | 4.3 | 10 km |
North Red Bog Wind Onshore · Operational | 1.6 | 10.5 km |
Hillhead Of Gask, Longhaven -Battery Storage Battery · Under Construction | — | 10.8 km |
Hillhead Of Gask, Longhaven - Solar Array Solar Photovoltaics · Under Construction | 14.2 | 10.8 km |
St Fergus Moss Wind Farm Wind Onshore · Operational | 6 | 11.1 km |
How big is West Knock Wind Cluster?
West Knock Wind Cluster has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates West Knock Wind Cluster?
REPD records the operator as West Knock Farm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was West Knock Wind Cluster approved and built?
The application was submitted on 2009-07-27. Permission was granted on 2011-04-21, 21 months later. The site became operational on 2011-10-04, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3681.