Novarly ParcelRenewable sites

Renewable sitesWest Knock Wind Cluster

West Knock Wind Cluster

West Knock Wind Cluster is an operational 2.4 MW onshore wind farm in Aberdeenshire, generating since 4 October 2011. Planning permission was granted on 21 April 2011, 21 months after submission. Operator of record: West Knock Farm.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 4 October 2011
Wind Onshore
Technology
West Knock Farm
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted27 July 2009
Permission granted21 April 2011
21 months after submission
Operational4 October 2011
5 months after consent

Screening a site of your own?

RedlineUK · £39

Aberdeenshire approves 69% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with West Knock Wind Cluster’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Aberdeenshire’s record on onshore wind

Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
18.7 km
Wind Onshore · Operational
6.99.4 km
Wind Onshore · Operational
2.49.9 km
Landfill Gas · Operational
4.310 km
Wind Onshore · Operational
1.610.5 km
Battery · Under Construction
10.8 km
Solar Photovoltaics · Under Construction
14.210.8 km
Wind Onshore · Operational
611.1 km

How big is West Knock Wind Cluster?

West Knock Wind Cluster has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates West Knock Wind Cluster?

REPD records the operator as West Knock Farm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was West Knock Wind Cluster approved and built?

The application was submitted on 27 July 2009. Permission was granted on 21 April 2011, 21 months later. The site became operational on 4 October 2011, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3681.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode