North Red Bog is operational in Aberdeenshire with a recorded capacity of 1.6 MW, and has been generating since 2008-06-23.
Planning and build timeline
| Application submitted | 2007-07-06 |
| Permission granted | 2008-03-07 8 months after submission |
| Operational | 2008-06-23 4 months after consent |
Aberdeenshire’s record on onshore wind
Aberdeenshire has decided 118 onshore wind schemes and approved 69%, taking a median of 12.7 months. See every onshore wind scheme decision in Aberdeenshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
House O�Hill Solar Farm Solar Photovoltaics · Operational | 1.6 | 4.3 km |
House O'Hill Wind Onshore · Operational | 5 | 4.3 km |
Mains of Hatton Wind Onshore · Operational | 2.4 | 4.6 km |
Bilbo Solar Farm Solar Photovoltaics · Under Construction | 36.6 | 5.8 km |
Bilbo Solar Farm Energy Storage Battery · Under Construction | 40 | 5.8 km |
St Fergus Moss Wind Farm Wind Onshore · Operational | 6 | 6.1 km |
Land at Overside and Greenwellheads Farms Wind Onshore · Operational | 9.2 | 6.6 km |
Bruxiehall Farm Solar Photovoltaics · Under Construction | 2 | 10.2 km |
How big is North Red Bog?
North Red Bog has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates North Red Bog?
REPD records the operator as Green Cat Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was North Red Bog approved and built?
The application was submitted on 2007-07-06. Permission was granted on 2008-03-07, 8 months later. The site became operational on 2008-06-23, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2965.