Renewable sitesHillhead Of Gask, Longhaven -Battery Storage

Hillhead Of Gask, Longhaven -Battery Storage

Hillhead Of Gask, Longhaven -Battery Storage is under construction in Aberdeenshire.

Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
The Greenspan Agency
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted2022-01-14
Permission granted2022-04-08
3 months after submission
Operationalnot recorded

Aberdeenshire’s record on battery storage

Aberdeenshire has decided 27 battery storage schemes and approved 96%, taking a median of 5.7 months. See every battery storage scheme decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Hillhead Of Gask, Longhaven - Solar Array
Solar Photovoltaics · Under Construction
14.20 km
Stoneyhill Landfill Site
Landfill Gas · Operational
4.31.1 km
Hywind 2
Battery · Operational
16.2 km
Yonderton Farm
Wind Onshore · Operational
16.3 km
Bruxiehall Farm
Solar Photovoltaics · Under Construction
29.7 km
West Knock Wind Cluster
Wind Onshore · Operational
2.410.8 km
St Fergus Renewable Energy Park
Battery · Under Construction
11.5 km
St Fergus Renewable Energy Park
Wind Onshore · Under Construction
311.5 km

How big is Hillhead Of Gask, Longhaven -Battery Storage?

REPD does not record an installed capacity for Hillhead Of Gask, Longhaven -Battery Storage.

Who operates Hillhead Of Gask, Longhaven -Battery Storage?

REPD records the operator as The Greenspan Agency. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hillhead Of Gask, Longhaven -Battery Storage approved and built?

The application was submitted on 2022-01-14. Permission was granted on 2022-04-08, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10470.