Renewable sites › West Farm (Solar)
West Farm (Solar)
West Farm (Solar) is operational in Pembrokeshire with a recorded capacity of 7.7 MW, and has been generating since 2013-03-28.
Planning and build timeline
| Application submitted | 2012-05-01 |
| Permission granted | 2012-11-28 7 months after submission |
| Operational | 2013-03-28 4 months after consent |
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
West Farm, Cosheston - Solar Farm Solar Photovoltaics · Under Construction | 9 | 0.3 km |
Golden Hill Solar Photovoltaics · Operational | 6.2 | 1.6 km |
Dragon Energy Park - Wind Farm Wind Onshore · Under Construction | 14.4 | 6.2 km |
Wear Point Wind Onshore · Operational | 8.2 | 6.6 km |
Dragon Long Meadow - Solar farm Solar Photovoltaics · Operational | 9.9 | 7.1 km |
Chapel Hill Solar Photovoltaics · Operational | 8 | 7.1 km |
Jordanston Solar Farm Solar Photovoltaics · Operational | 5 | 7.7 km |
Castle Pill - Repowering Wind Onshore · Operational | 3.2 | 8.1 km |
How big is West Farm (Solar)?
West Farm (Solar) has a recorded installed capacity of 7.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates West Farm (Solar)?
REPD records the operator as Vogt Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was West Farm (Solar) approved and built?
The application was submitted on 2012-05-01. Permission was granted on 2012-11-28, 7 months later. The site became operational on 2013-03-28, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1244.