Novarly ParcelRenewable sites

Renewable sitesBlack Law Extension - 1a

Black Law Extension - 1a

Black Law Extension - 1a is operational in Scottish Government (S36) with a recorded capacity of 48.4 MW, and has been generating since 2016-02-18.

48.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-02-18
Wind Onshore
Technology
Scottish Power Renewables
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2008-01-25
Permission granted2011-03-22
38 months after submission
Operational2016-02-18
59 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Black Law Extension - 1b
Wind Onshore · Operational
150 km
Black Law
Wind Onshore · Operational
1240 km
Watsonhead Wind Farm
Wind Onshore · Operational
8.45.3 km
Levenseat EfW
Advanced Conversion Technologies · Operational
12.55.6 km
Levenseat Waste Management Facility
Advanced Conversion Technologies · Operational
176 km
Sewage Treatment Works, Rosehall Road - Solar PV Panels
Solar Photovoltaics · Under Construction
0.236.6 km
Tormywheel
Wind Onshore · Operational
30.757.4 km
West Benhar wind farm
Wind Onshore · Operational
27.28.3 km

How big is Black Law Extension - 1a?

Black Law Extension - 1a has a recorded installed capacity of 48.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Black Law Extension - 1a?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Black Law Extension - 1a approved and built?

The application was submitted on 2008-01-25. Permission was granted on 2011-03-22, 38 months later. The site became operational on 2016-02-18, 59 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4253.