Novarly ParcelRenewable sites

Renewable sitesBlack Law Extension - 1a

Black Law Extension - 1a

Black Law Extension - 1a is an operational 48.4 MW onshore wind farm in Scotland, generating since 18 February 2016. Planning permission was granted on 22 March 2011, 38 months after submission. Operator of record: Scottish Power Renewables.

48.4 MW
Capacity
as recorded in REPD
Operational
Status
since 18 February 2016
Wind Onshore
Technology
Scottish Power Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted25 January 2008
Permission granted22 March 2011
38 months after submission
Operational18 February 2016
59 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Black Law Extension - 1a’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
1240 km
Wind Onshore · Operational
150 km
Wind Onshore · Operational
8.45.3 km
Advanced Conversion Technologies · Operational
12.55.6 km
Advanced Conversion Technologies · Operational
176 km
Solar Photovoltaics · Under Construction
0.236.6 km
Wind Onshore · Operational
30.757.4 km
Wind Onshore · Operational
27.28.3 km

How big is Black Law Extension - 1a?

Black Law Extension - 1a has a recorded installed capacity of 48.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Black Law Extension - 1a?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Black Law Extension - 1a approved and built?

The application was submitted on 25 January 2008. Permission was granted on 22 March 2011, 38 months later. The site became operational on 18 February 2016, 59 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4253.