Renewable sites › Kilsby Landfill Scheme
Kilsby Landfill Scheme
Kilsby Landfill Scheme is operational in West Northamptonshire with a recorded capacity of 1 MW, and has been generating since 1998-11-05.
Planning and build timeline
| Application submitted | 1997-10-10 |
| Permission granted | 1998-02-12 4 months after submission |
| Operational | 1998-11-05 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
M1 J18 Wind Turbines Wind Onshore · Operational | 4 | 3.3 km |
Watford Lodge Wind Onshore · Operational | 12.5 | 4.2 km |
Crick Road Solar Photovoltaics · Under Construction | 49.9 | 4.9 km |
Yelvertoft Wind Farm Wind Onshore · Operational | 16 | 6.1 km |
Royal Oak Way South - Solar Array Solar Photovoltaics · Operational | 1.66 | 6.5 km |
Daventry Biomass (dedicated) · Operational | 1 | 7.3 km |
Lilbourne Wind Farm Wind Onshore · Operational | 10 | 8.2 km |
Winwick Wind Onshore · Operational | 12.3 | 8.8 km |
How big is Kilsby Landfill Scheme?
Kilsby Landfill Scheme has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kilsby Landfill Scheme?
REPD records the operator as Hales Waste Control Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kilsby Landfill Scheme approved and built?
The application was submitted on 1997-10-10. Permission was granted on 1998-02-12, 4 months later. The site became operational on 1998-11-05, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 535.
Novarly Parcel · official public data, read properly · parcel.novarly.com