Novarly ParcelRenewable sites

Renewable sitesWalkway

Walkway

Walkway is operational in County Durham with a recorded capacity of 14 MW, and has been generating since 2008-05-15.

14 MW
Capacity
as recorded in REPD
Operational
Status
since 2008-05-15
Wind Onshore
Technology
Wind Prospect
County Durham
Authority
England

Planning and build timeline

Application submitted2004-11-01
Permission granted2005-02-20
4 months after submission
Operational2008-05-15
39 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

County Durham’s record on onshore wind

County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham

Other built sites within 15 km

SiteMWDistance
Butterwick Moor
Wind Onshore · Operational
20.50 km
Red Gap Moor Wind Farm
Wind Onshore · Operational
12.55.3 km
Cowley Complex, Stockton on Tees
Solar Photovoltaics · Under Construction
1205.7 km
Southern Law
Wind Onshore · Operational
5.27 km
Trimdon Grange
Wind Onshore · Operational
5.27 km
High Volts Wind Farm
Wind Onshore · Operational
5.57.1 km
Stob House Farm
Solar Photovoltaics · Operational
4.97.3 km
High Meadow Farm
Solar Photovoltaics · Operational
48.2 km

How big is Walkway?

Walkway has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Walkway?

REPD records the operator as Wind Prospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Walkway approved and built?

The application was submitted on 2004-11-01. Permission was granted on 2005-02-20, 4 months later. The site became operational on 2008-05-15, 39 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3606.