Novarly ParcelRenewable sites

Renewable sitesHigh Meadow Farm

High Meadow Farm

High Meadow Farm is operational in Stockton-on-Tees with a recorded capacity of 4 MW, and has been generating since 2016-10-18.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-10-18
Solar Photovoltaics
Technology
Anesco
Stockton-on-Tees
Authority
England

Planning and build timeline

Application submitted2015-07-22
Permission granted2015-12-04
4 months after submission
Operational2016-10-18
10 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Stockton-on-Tees’s record on solar

Stockton-on-Tees has decided 19 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Stockton-on-Tees

Other built sites within 15 km

SiteMWDistance
Cowley Complex, Stockton on Tees
Solar Photovoltaics · Under Construction
1202.5 km
Eaglescliffe Solar Farm
Solar Photovoltaics · Operational
55.8 km
Lambs Hill
Wind Onshore · Operational
86 km
Billingham Chemical Works
EfW Incineration · Operational
126.7 km
Stob House Farm
Solar Photovoltaics · Operational
4.97.1 km
Red Gap Moor Wind Farm
Wind Onshore · Operational
12.57.2 km
Haverton Hill Incinerator
EfW Incineration · Operational
20.17.6 km
North East Energy Recovery Centre (adjacent to Teesside EfW)
EfW Incineration · Operational
217.7 km

How big is High Meadow Farm?

High Meadow Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates High Meadow Farm?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was High Meadow Farm approved and built?

The application was submitted on 2015-07-22. Permission was granted on 2015-12-04, 4 months later. The site became operational on 2016-10-18, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6321.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council