Renewable sites › Southern Law
Southern Law
Southern Law is operational in County Durham with a recorded capacity of 5.2 MW, and has been generating since 2008-07-10.
Planning and build timeline
| Application submitted | 2004-08-13 |
| Permission granted | 2005-07-01 11 months after submission |
| Operational | 2008-07-10 36 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
County Durham’s record on onshore wind
County Durham has decided 30 onshore wind schemes and approved 63%, taking a median of 10.5 months. See every onshore wind scheme decision in County Durham →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Trimdon Grange Wind Onshore · Operational | 5.2 | 0.5 km |
PG1-Coxhoe Waste Disposal Site Landfill Gas · Operational | 3.8 | 3.7 km |
Hare Hill (B) Wind Onshore · Operational | 2.7 | 4.6 km |
Hare Hill Wind Onshore · Operational | 1.3 | 4.6 km |
Haswell Moor Wind Onshore · Operational | 10 | 5.1 km |
Butterwick Moor Wind Onshore · Operational | 20.5 | 7 km |
Walkway Wind Onshore · Operational | 14 | 7 km |
B H K UK Davy Drive - Solar Panels Solar Photovoltaics · Under Construction | 1.34 | 7.1 km |
How big is Southern Law?
Southern Law has a recorded installed capacity of 5.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Southern Law?
REPD records the operator as EDF Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Southern Law approved and built?
The application was submitted on 2004-08-13. Permission was granted on 2005-07-01, 11 months later. The site became operational on 2008-07-10, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3223.
Novarly Parcel · official public data, read properly · parcel.novarly.com