Novarly ParcelRenewable sites

Renewable sitesRed Gap Moor Wind Farm

Red Gap Moor Wind Farm

Red Gap Moor Wind Farm is operational in Hartlepool with a recorded capacity of 12.5 MW, and has been generating since 2017-02-15.

12.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-02-15
Wind Onshore
Technology
Capital Dynamics
Hartlepool
Authority
England

Planning and build timeline

Application submitted2009-05-20
Permission granted2011-03-31
22 months after submission
Operational2017-02-15
71 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Stob House Farm
Solar Photovoltaics · Operational
4.92.2 km
Land at Bluehouse Farm
Solar Photovoltaics · Operational
53.7 km
Walkway
Wind Onshore · Operational
145.3 km
Butterwick Moor
Wind Onshore · Operational
20.55.3 km
High Volts Wind Farm
Wind Onshore · Operational
5.55.4 km
Cowley Complex, Stockton on Tees
Solar Photovoltaics · Under Construction
1206 km
North East Energy Recovery Centre (adjacent to Teesside EfW)
EfW Incineration · Operational
216.9 km
Teesside EfW (extension)
EfW Incineration · Operational
106.9 km

How big is Red Gap Moor Wind Farm?

Red Gap Moor Wind Farm has a recorded installed capacity of 12.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Red Gap Moor Wind Farm?

REPD records the operator as Capital Dynamics. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Red Gap Moor Wind Farm approved and built?

The application was submitted on 2009-05-20. Permission was granted on 2011-03-31, 22 months later. The site became operational on 2017-02-15, 71 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4415.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council