Novarly ParcelRenewable sites

Renewable sitesPort of Tyne

Port of Tyne

Port of Tyne is operational in South Tyneside with a recorded capacity of 35 MW, and has been generating since 2018-07-01.

35 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-07-01
Battery
Technology
Foresight
South Tyneside
Authority
England

Planning and build timeline

Application submitted2016-09-07
Permission grantednot recorded
Operational2018-07-01

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Standby Embedded Stor Power Plant - Battery storage
Battery · Under Construction
203.4 km
Howdon STW
Sewage Sludge Digestion · Operational
63.7 km
Tynemouth Energy Storage System (TESS)
Battery · Operational
256.2 km
Nissan Test Track
Solar Photovoltaics · Operational
4.86.3 km
Unipres building
Solar Photovoltaics · Operational
4.96.8 km
Nissan Wind Farm
Wind Onshore · Operational
47.2 km
Nissan Motors Plant Extn
Wind Onshore · Operational
27.2 km
Regent Street - Solar Photovoltaic Panels
Solar Photovoltaics · Operational
9.6 km

How big is Port of Tyne?

Port of Tyne has a recorded installed capacity of 35 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Port of Tyne?

REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Port of Tyne approved and built?

The application was submitted on 2016-09-07. REPD does not record a grant date. The site became operational on 2018-07-01.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6976.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council