Tye Lane - Solar Farm

Tye Lane - Solar Farm is operational in Mid Suffolk, and has been generating since 2026-02-20.

Capacity
as recorded in REPD
Operational
Status
since 2026-02-20
Battery
Technology
EDF Energy Renewables
Mid Suffolk
Authority
England

Planning and build timeline

Application submitted2021-09-02
Permission granted2023-12-18
27 months after submission
Operational2026-02-20
26 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Mid Suffolk’s record on battery storage

Mid Suffolk has decided 11 battery storage schemes and approved 100%, taking a median of 5.8 months. See every battery storage scheme decision in Mid Suffolk

Other built sites within 15 km

SiteMWDistance
Tye Lane - Solar Farm
Solar Photovoltaics · Under Construction
49.90 km
Bullen Lane - Battery Storage
Battery · Under Construction
1001.4 km
Bramford Substation
Battery · Operational
571.5 km
Great Blakenham EfW
EfW Incineration · Operational
202.7 km
Masons Power Plant Landfill Scheme
Landfill Gas · Operational
5.52.8 km
University Of Suffolk Campus North
Battery · Operational
6.9 km
Mid Suffolk Home Solar Scheme
Solar Photovoltaics · Operational
4.88.2 km
Ipswich Hospital Energy Centre
Biomass (dedicated) · Operational
2.68.8 km

How big is Tye Lane - Solar Farm?

REPD does not record an installed capacity for Tye Lane - Solar Farm.

Who operates Tye Lane - Solar Farm?

REPD records the operator as EDF Energy Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tye Lane - Solar Farm approved and built?

The application was submitted on 2021-09-02. Permission was granted on 2023-12-18, 27 months later. The site became operational on 2026-02-20, 26 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 20402.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council