Renewable sites › Tye Lane - Solar Farm
Tye Lane - Solar Farm
Tye Lane - Solar Farm is operational in Mid Suffolk, and has been generating since 2026-02-20.
Planning and build timeline
| Application submitted | 2021-09-02 |
| Permission granted | 2023-12-18 27 months after submission |
| Operational | 2026-02-20 26 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Mid Suffolk’s record on battery storage
Mid Suffolk has decided 11 battery storage schemes and approved 100%, taking a median of 5.8 months. See every battery storage scheme decision in Mid Suffolk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tye Lane - Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 0 km |
Bullen Lane - Battery Storage Battery · Under Construction | 100 | 1.4 km |
Bramford Substation Battery · Operational | 57 | 1.5 km |
Great Blakenham EfW EfW Incineration · Operational | 20 | 2.7 km |
Masons Power Plant Landfill Scheme Landfill Gas · Operational | 5.5 | 2.8 km |
University Of Suffolk Campus North Battery · Operational | — | 6.9 km |
Mid Suffolk Home Solar Scheme Solar Photovoltaics · Operational | 4.8 | 8.2 km |
Ipswich Hospital Energy Centre Biomass (dedicated) · Operational | 2.6 | 8.8 km |
How big is Tye Lane - Solar Farm?
REPD does not record an installed capacity for Tye Lane - Solar Farm.
Who operates Tye Lane - Solar Farm?
REPD records the operator as EDF Energy Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tye Lane - Solar Farm approved and built?
The application was submitted on 2021-09-02. Permission was granted on 2023-12-18, 27 months later. The site became operational on 2026-02-20, 26 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 20402.