Renewable sites › Ipswich Hospital Energy Centre
Ipswich Hospital Energy Centre
Ipswich Hospital Energy Centre is operational in Ipswich with a recorded capacity of 2.6 MW, and has been generating since 2017-03-15.
Planning and build timeline
| Application submitted | 2012-12-24 |
| Permission granted | 2013-02-19 2 months after submission |
| Operational | 2017-03-15 49 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
University Of Suffolk Campus North Battery · Operational | — | 2.3 km |
Foxhall Landfill Site Landfill Gas · Operational | 1.2 | 4.6 km |
Foxburrow Farm Solar Photovoltaics · Operational | 8 | 6.1 km |
Bullen Lane - Battery Storage Battery · Under Construction | 100 | 7.4 km |
Stratton Hall Solar Park Solar Photovoltaics · Operational | 11.6 | 8.1 km |
Great Blakenham EfW EfW Incineration · Operational | 20 | 8.6 km |
Tye Lane - Solar Farm Battery · Operational | — | 8.8 km |
Tye Lane - Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 8.8 km |
How big is Ipswich Hospital Energy Centre?
Ipswich Hospital Energy Centre has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ipswich Hospital Energy Centre?
REPD records the operator as Naturegen Energy Centre. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ipswich Hospital Energy Centre approved and built?
The application was submitted on 2012-12-24. Permission was granted on 2013-02-19, 2 months later. The site became operational on 2017-03-15, 49 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6507.