Renewable sites › Masons Power Plant Landfill Scheme
Masons Power Plant Landfill Scheme
Masons Power Plant Landfill Scheme is operational in Mid Suffolk with a recorded capacity of 5.5 MW, and has been generating since 2008-02-26.
Planning and build timeline
| Application submitted | 1997-03-20 |
| Permission granted | 1997-06-19 3 months after submission |
| Operational | 2008-02-26 128 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Great Blakenham EfW EfW Incineration · Operational | 20 | 1.3 km |
Tye Lane - Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 2.8 km |
Tye Lane - Solar Farm Battery · Operational | — | 2.8 km |
Bullen Lane - Battery Storage Battery · Under Construction | 100 | 3.6 km |
Bramford Substation Battery · Operational | 57 | 4.2 km |
Mid Suffolk Home Solar Scheme Solar Photovoltaics · Operational | 4.8 | 5.8 km |
University Of Suffolk Campus North Battery · Operational | — | 8.4 km |
Ipswich Hospital Energy Centre Biomass (dedicated) · Operational | 2.6 | 9.9 km |
How big is Masons Power Plant Landfill Scheme?
Masons Power Plant Landfill Scheme has a recorded installed capacity of 5.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Masons Power Plant Landfill Scheme?
REPD records the operator as Haul Waste Disposal Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Masons Power Plant Landfill Scheme approved and built?
The application was submitted on 1997-03-20. Permission was granted on 1997-06-19, 3 months later. The site became operational on 2008-02-26, 128 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 522.
Novarly Parcel · official public data, read properly · parcel.novarly.com