Trigon Solar Farm

Trigon Solar Farm is operational in Dorset with a recorded capacity of 7 MW, and has been generating since 2013-03-08.

7 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-08
Solar Photovoltaics
Technology
Trigon Solar Farm Ltd
Dorset
Authority
England

Planning and build timeline

Application submitted2012-07-05
Permission granted2012-11-28
5 months after submission
Operational2013-03-08
3 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Dorset’s record on solar

Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset

Other built sites within 15 km

SiteMWDistance
Bottom Plain
Solar Photovoltaics · Operational
100.6 km
Oaklands Plantation
Solar Photovoltaics · Operational
52.2 km
Stokeford Farm
Solar Photovoltaics · Operational
28.52.7 km
Woolbridge Solar Park
Solar Photovoltaics · Operational
54.3 km
Slepe Farm
Battery · Operational
0.36 km
South Newton Farm
Solar Photovoltaics · Operational
11.36.1 km
Dolmans Hill (Redbridge Farm) Solar Arrays
Solar Photovoltaics · Operational
56.7 km
North of Newton Farm
Solar Photovoltaics · Operational
36.7 km

How big is Trigon Solar Farm?

Trigon Solar Farm has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Trigon Solar Farm?

REPD records the operator as Trigon Solar Farm Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Trigon Solar Farm approved and built?

The application was submitted on 2012-07-05. Permission was granted on 2012-11-28, 5 months later. The site became operational on 2013-03-08, 3 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1060.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council