Renewable sitesSlepe Farm

Slepe Farm

Slepe Farm is an operational 0.3 MW battery storage site in Dorset, generating since 10 October 2014. Planning permission was granted on 8 August 2011, 2 months after submission. Operator of record: Farm Power Apollo/ Anesco.

0.3 MW
Capacity
as recorded in REPD
Operational
Status
since 10 October 2014
Battery
Technology
Farm Power Apollo/ Anesco
Dorset
Authority
England

Planning and build timeline

Application submitted21 June 2011
Permission granted8 August 2011
2 months after submission
Operational10 October 2014
38 months after consent

Screening a site of your own?

RedlineUK · £39

Dorset approves 87% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Slepe Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Dorset’s record on battery storage

Dorset has decided 15 battery storage schemes and approved 87%, taking a median of 7 months. See every battery storage scheme decision in Dorset

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
11.30.5 km
Solar Photovoltaics · Operational
30.8 km
Solar Photovoltaics · Operational
51.3 km
Solar Photovoltaics · Operational
6.13 km
Solar Photovoltaics · Operational
54.8 km
Landfill Gas · Operational
35.3 km
Solar Photovoltaics · Operational
3.95.4 km
Solar Photovoltaics · Operational
105.4 km

How big is Slepe Farm?

Slepe Farm has a recorded installed capacity of 0.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Slepe Farm?

REPD records the operator as Farm Power Apollo/ Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Slepe Farm approved and built?

The application was submitted on 21 June 2011. Permission was granted on 8 August 2011, 2 months later. The site became operational on 10 October 2014, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6866.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode