Novarly ParcelRenewable sites

Renewable sitesNorth of Newton Farm

North of Newton Farm

North of Newton Farm is operational in Dorset with a recorded capacity of 3 MW, and has been generating since 2014-03-19.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-19
Solar Photovoltaics
Technology
Primrose Solar
Dorset
Authority
England

Planning and build timeline

Application submitted2013-03-06
Permission granted2013-06-28
4 months after submission
Operational2014-03-19
9 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Dorset’s record on solar

Dorset has decided 97 solar farms and approved 95%, taking a median of 3.7 months. See every solar farm decision in Dorset

Other built sites within 15 km

SiteMWDistance
Slepe Farm
Battery · Operational
0.30.8 km
Dolmans Hill (Redbridge Farm) Solar Arrays
Solar Photovoltaics · Operational
50.8 km
South Newton Farm
Solar Photovoltaics · Operational
11.31.1 km
Race farm
Solar Photovoltaics · Operational
6.12.4 km
Henbury Quarry
Solar Photovoltaics · Operational
3.94.6 km
Beacon Hill
Landfill Gas · Operational
34.7 km
Oaklands Plantation
Solar Photovoltaics · Operational
55.6 km
Bottom Plain
Solar Photovoltaics · Operational
106.1 km

How big is North of Newton Farm?

North of Newton Farm has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates North of Newton Farm?

REPD records the operator as Primrose Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was North of Newton Farm approved and built?

The application was submitted on 2013-03-06. Permission was granted on 2013-06-28, 4 months later. The site became operational on 2014-03-19, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2047.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council