Renewable sites › Torrance Farm Wind Park Extension
Torrance Farm Wind Park Extension
Torrance Farm Wind Park Extension is operational in North Lanarkshire with a recorded capacity of 5.7 MW, and has been generating since 2015-06-18.
Planning and build timeline
| Application submitted | 2012-03-19 |
| Permission granted | 2012-07-31 4 months after submission |
| Operational | 2015-06-18 35 months after consent |
North Lanarkshire’s record on onshore wind
North Lanarkshire has decided 20 onshore wind schemes and approved 70%, taking a median of 16.8 months. See every onshore wind scheme decision in North Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Torrance Farm Wind Onshore · Operational | 9 | 0.5 km |
Southrigg Wind Onshore · Operational | 1.5 | 1.2 km |
Drumduff Wind Onshore · Operational | 8.5 | 3.7 km |
Burnhead Wind Onshore · Operational | 26 | 4.4 km |
Brownhill Farm Wind Onshore · Under Construction | 8.4 | 4.5 km |
West Benhar wind farm Wind Onshore · Operational | 27.2 | 4.7 km |
Aldi Distribution Centre Solar Photovoltaics · Operational | 1.3 | 6.1 km |
Sewage Treatment Works, Rosehall Road - Solar PV Panels Solar Photovoltaics · Under Construction | 0.23 | 8.1 km |
How big is Torrance Farm Wind Park Extension?
Torrance Farm Wind Park Extension has a recorded installed capacity of 5.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Torrance Farm Wind Park Extension?
REPD records the operator as Capital Dynamics. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Torrance Farm Wind Park Extension approved and built?
The application was submitted on 2012-03-19. Permission was granted on 2012-07-31, 4 months later. The site became operational on 2015-06-18, 35 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4085.