Novarly ParcelRenewable sites

Renewable sitesTorrance Farm

Torrance Farm

Torrance Farm is operational in North Lanarkshire with a recorded capacity of 9 MW, and has been generating since 2013-12-30.

9 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-12-30
Wind Onshore
Technology
Future Spectrum Ltd
North Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted2010-08-30
Permission granted2011-02-24
6 months after submission
Operational2013-12-30
34 months after consent

North Lanarkshire’s record on onshore wind

North Lanarkshire has decided 20 onshore wind schemes and approved 70%, taking a median of 16.8 months. See every onshore wind scheme decision in North Lanarkshire

Other built sites within 15 km

SiteMWDistance
Torrance Farm Wind Park Extension
Wind Onshore · Operational
5.70.5 km
Southrigg
Wind Onshore · Operational
1.51 km
Brownhill Farm
Wind Onshore · Under Construction
8.44 km
West Benhar wind farm
Wind Onshore · Operational
27.24.1 km
Drumduff
Wind Onshore · Operational
8.54.2 km
Burnhead
Wind Onshore · Operational
264.8 km
Aldi Distribution Centre
Solar Photovoltaics · Operational
1.36.2 km
Sewage Treatment Works, Rosehall Road - Solar PV Panels
Solar Photovoltaics · Under Construction
0.237.6 km

How big is Torrance Farm?

Torrance Farm has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Torrance Farm?

REPD records the operator as Future Spectrum Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Torrance Farm approved and built?

The application was submitted on 2010-08-30. Permission was granted on 2011-02-24, 6 months later. The site became operational on 2013-12-30, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3799.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council