Novarly ParcelRenewable sites

Renewable sitesBurnhead

Burnhead

Burnhead is an operational 26 MW onshore wind farm in Falkirk, generating since 29 February 2016. Planning permission was granted on 8 October 2013, 34 months after submission. Operator of record: Wind Prospect Developments/ EDF.

26 MW
Capacity
as recorded in REPD
Operational
Status
since 29 February 2016
Wind Onshore
Technology
Wind Prospect Developments/ EDF
Falkirk
Authority
Scotland

Planning and build timeline

Application submitted17 December 2010
Permission granted8 October 2013
34 months after submission
Operational29 February 2016
29 months after consent

Screening a site of your own?

RedlineUK · £39

Falkirk approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Burnhead’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Falkirk’s record on onshore wind

Falkirk has decided 5 onshore wind schemes and approved 80%, taking a median of 11.7 months. See every onshore wind scheme decision in Falkirk

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
8.50.9 km
Wind Onshore · Operational
5.74.4 km
Wind Onshore · Operational
94.8 km
Wind Onshore · Operational
1.55.4 km
Wind Onshore · Operational
48 km
Wind Onshore · Under Construction
8.48.1 km
Wind Onshore · Operational
27.28.5 km
Wind Onshore · Operational
248.7 km

How big is Burnhead?

Burnhead has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Burnhead?

REPD records the operator as Wind Prospect Developments/ EDF. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Burnhead approved and built?

The application was submitted on 17 December 2010. Permission was granted on 8 October 2013, 34 months later. The site became operational on 29 February 2016, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4125.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode