Renewable sites › Burnhead
Burnhead
Burnhead is operational in Falkirk with a recorded capacity of 26 MW, and has been generating since 2016-02-29.
Planning and build timeline
| Application submitted | 2010-12-17 |
| Permission granted | 2013-10-08 34 months after submission |
| Operational | 2016-02-29 29 months after consent |
Falkirk’s record on onshore wind
Falkirk has decided 5 onshore wind schemes and approved 80%, taking a median of 11.7 months. See every onshore wind scheme decision in Falkirk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Drumduff Wind Onshore · Operational | 8.5 | 0.9 km |
Torrance Farm Wind Park Extension Wind Onshore · Operational | 5.7 | 4.4 km |
Torrance Farm Wind Onshore · Operational | 9 | 4.8 km |
Southrigg Wind Onshore · Operational | 1.5 | 5.4 km |
Greendykeside Wind Onshore · Operational | 4 | 8 km |
Brownhill Farm Wind Onshore · Under Construction | 8.4 | 8.1 km |
West Benhar wind farm Wind Onshore · Operational | 27.2 | 8.5 km |
Greengairs East Wind Farm Wind Onshore · Operational | 24 | 8.7 km |
How big is Burnhead?
Burnhead has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Burnhead?
REPD records the operator as Wind Prospect Developments/ EDF. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Burnhead approved and built?
The application was submitted on 2010-12-17. Permission was granted on 2013-10-08, 34 months later. The site became operational on 2016-02-29, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4125.
Novarly Parcel · official public data, read properly · parcel.novarly.com