Novarly ParcelRenewable sites

Renewable sitesDrumduff

Drumduff

Drumduff is operational in West Lothian with a recorded capacity of 8.5 MW, and has been generating since 2017-07-11.

8.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-07-11
Wind Onshore
Technology
Green Breeze Energy Ltd
West Lothian
Authority
Scotland

Planning and build timeline

Application submitted2014-02-26
Permission granted2015-06-18
16 months after submission
Operational2017-07-11
25 months after consent

West Lothian’s record on onshore wind

West Lothian has decided 13 onshore wind schemes and approved 85%, taking a median of 11.3 months. See every onshore wind scheme decision in West Lothian

Other built sites within 15 km

SiteMWDistance
Burnhead
Wind Onshore · Operational
260.9 km
Torrance Farm Wind Park Extension
Wind Onshore · Operational
5.73.7 km
Torrance Farm
Wind Onshore · Operational
94.2 km
Southrigg
Wind Onshore · Operational
1.54.8 km
Brownhill Farm
Wind Onshore · Under Construction
8.47.2 km
West Benhar wind farm
Wind Onshore · Operational
27.27.6 km
Greendykeside
Wind Onshore · Operational
47.8 km
Greengairs East Wind Farm
Wind Onshore · Operational
248.3 km

How big is Drumduff?

Drumduff has a recorded installed capacity of 8.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Drumduff?

REPD records the operator as Green Breeze Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Drumduff approved and built?

The application was submitted on 2014-02-26. Permission was granted on 2015-06-18, 16 months later. The site became operational on 2017-07-11, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4218.

Novarly Parcel · official public data, read properly · parcel.novarly.com