Ridham CHP Plant is operational in Swale with a recorded capacity of 25 MW, and has been generating since 2016-04-18.

25 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-04-18
Biomass (dedicated)
Technology
MVV Energie, Ridham Dock
Swale
Authority
England

Planning and build timeline

Application submitted2010-06-29
Permission granted2012-05-28
23 months after submission
Operational2016-04-18
47 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Morrisons roof mounted solar
Solar Photovoltaics · Operational
21.5 km
K3 CHP Facility (Kemsley EfW)
EfW Incineration · Operational
49.91.7 km
Kemsley Substation
Battery · Operational
49.92.1 km
Land off Queenborough Road
Battery · Under Construction
403 km
Tonge Corner Farm
Solar Photovoltaics · Operational
223.4 km
South Lees Farm
Solar Photovoltaics · Operational
113.9 km
Plot 2B EurolinkV
Battery · Under Construction
204.1 km
Orchard Farm
Solar Photovoltaics · Operational
104.4 km

How big is Ridham CHP Plant?

Ridham CHP Plant has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ridham CHP Plant?

REPD records the operator as MVV Energie, Ridham Dock. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ridham CHP Plant approved and built?

The application was submitted on 2010-06-29. Permission was granted on 2012-05-28, 23 months later. The site became operational on 2016-04-18, 47 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 106.