Ridham CHP Plant is an operational 25 MW biomass plant in Swale, generating since 18 April 2016. Planning permission was granted on 28 May 2012, 23 months after submission. Operator of record: MVV Energie, Ridham Dock.

25 MW
Capacity
as recorded in REPD
Operational
Status
since 18 April 2016
Biomass (dedicated)
Technology
MVV Energie, Ridham Dock
Swale
Authority
England

Planning and build timeline

Application submitted29 June 2010
Permission granted28 May 2012
23 months after submission
Operational18 April 2016
47 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Swale: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ridham CHP Plant’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
21.5 km
EfW Incineration · Operational
49.91.7 km
Battery · Operational
49.92.1 km
Battery · Under Construction
403 km
Solar Photovoltaics · Operational
223.4 km
Solar Photovoltaics · Operational
113.9 km
Battery · Under Construction
204.1 km
Solar Photovoltaics · Operational
104.4 km

How big is Ridham CHP Plant?

Ridham CHP Plant has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ridham CHP Plant?

REPD records the operator as MVV Energie, Ridham Dock. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ridham CHP Plant approved and built?

The application was submitted on 29 June 2010. Permission was granted on 28 May 2012, 23 months later. The site became operational on 18 April 2016, 47 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 106.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode