Renewable sitesK3 CHP Facility (Kemsley EfW)

K3 CHP Facility (Kemsley EfW)

K3 CHP Facility (Kemsley EfW) is an operational 49.9 MW energy-from-waste plant in Swale, generating since 21 July 2020. Planning permission was granted on 13 July 2010, 4 months after submission. Operator of record: E.ON / Wheelabrator Technologies.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 21 July 2020
EfW Incineration
Technology
E.ON / Wheelabrator Technologies
Swale
Authority
England

Planning and build timeline

Application submitted23 March 2010
Permission granted13 July 2010
4 months after submission
Operational21 July 2020
120 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Swale: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with K3 CHP Facility (Kemsley EfW)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
21.1 km
Battery · Operational
49.91.1 km
Biomass (dedicated) · Operational
251.7 km
Solar Photovoltaics · Operational
222 km
Battery · Under Construction
202.4 km
Solar Photovoltaics · Operational
104.2 km
Battery · Under Construction
404.7 km
Solar Photovoltaics · Operational
11.35 km

How big is K3 CHP Facility (Kemsley EfW)?

K3 CHP Facility (Kemsley EfW) has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates K3 CHP Facility (Kemsley EfW)?

REPD records the operator as E.ON / Wheelabrator Technologies. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was K3 CHP Facility (Kemsley EfW) approved and built?

The application was submitted on 23 March 2010. Permission was granted on 13 July 2010, 4 months later. The site became operational on 21 July 2020, 120 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 946.