Novarly ParcelRenewable sites

Renewable sitesK3 CHP Facility (Kemsley EfW)

K3 CHP Facility (Kemsley EfW)

K3 CHP Facility (Kemsley EfW) is operational in Swale with a recorded capacity of 49.9 MW, and has been generating since 2020-07-21.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2020-07-21
EfW Incineration
Technology
E.ON / Wheelabrator Technologies
Swale
Authority
England

Planning and build timeline

Application submitted2010-03-23
Permission granted2010-07-13
4 months after submission
Operational2020-07-21
120 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Morrisons roof mounted solar
Solar Photovoltaics · Operational
21.1 km
Kemsley Substation
Battery · Operational
49.91.1 km
Ridham CHP Plant
Biomass (dedicated) · Operational
251.7 km
Tonge Corner Farm
Solar Photovoltaics · Operational
222 km
Plot 2B EurolinkV
Battery · Under Construction
202.4 km
Orchard Farm
Solar Photovoltaics · Operational
104.2 km
Land off Queenborough Road
Battery · Under Construction
404.7 km
Bobbing solar farm
Solar Photovoltaics · Operational
11.35 km

How big is K3 CHP Facility (Kemsley EfW)?

K3 CHP Facility (Kemsley EfW) has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates K3 CHP Facility (Kemsley EfW)?

REPD records the operator as E.ON / Wheelabrator Technologies. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was K3 CHP Facility (Kemsley EfW) approved and built?

The application was submitted on 2010-03-23. Permission was granted on 2010-07-13, 4 months later. The site became operational on 2020-07-21, 120 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 946.