Novarly ParcelRenewable sites

Renewable sitesMorrisons roof mounted solar

Morrisons roof mounted solar

Morrisons roof mounted solar is an operational 2 MW solar farm in Swale, generating since 15 November 2013. Planning permission was granted on 29 July 2013, 2 months after submission. Operator of record: WM Morrisons Supermarkets Plc.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 15 November 2013
Solar Photovoltaics
Technology
WM Morrisons Supermarkets Plc
Swale
Authority
England

Planning and build timeline

Application submitted28 May 2013
Permission granted29 July 2013
2 months after submission
Operational15 November 2013
4 months after consent

Screening a site of your own?

RedlineUK · £39

Swale approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Morrisons roof mounted solar’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Swale’s record on solar

Swale has decided 26 solar farms and approved 96%, taking a median of 2.5 months. See every solar farm decision in Swale

Other built sites within 15 km

SiteMWDistance
Battery · Operational
49.90.6 km
EfW Incineration · Operational
49.91.1 km
Biomass (dedicated) · Operational
251.5 km
Solar Photovoltaics · Operational
223.1 km
Solar Photovoltaics · Operational
103.2 km
Battery · Under Construction
203.3 km
Solar Photovoltaics · Operational
11.34.2 km
Battery · Under Construction
404.4 km

How big is Morrisons roof mounted solar?

Morrisons roof mounted solar has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Morrisons roof mounted solar?

REPD records the operator as WM Morrisons Supermarkets Plc. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Morrisons roof mounted solar approved and built?

The application was submitted on 28 May 2013. Permission was granted on 29 July 2013, 2 months later. The site became operational on 15 November 2013, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1237.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode